Project · Brooklyn, New York
DUMBO Street Reconstruction
DUMBO's cobblestone streets were falling behind the demands of a modern neighborhood. New York chose the painstaking option: take up hundreds of thousands of historic stones, rebuild the infrastructure underneath, and put them back. The work ran from 2019 to 2025 and cost $108 million.

The 26-block program required modern water and sewer lines, accessible crossings and bicycle routes within streets whose character depends on irregular stone paving. The city took up more than 800,000 cobblestones, stored them by block and returned them near their original locations.
New York City says the work installed or upgraded more than three miles of water mains and sewers. Crews added 114 accessible pedestrian ramps and 8,800 feet of smooth granite bicycle lanes, along with new curbs and the permanent Pearl Street Plaza. Drainage changes were designed to reduce combined sewage reaching the harbor during heavy rain.
Construction also uncovered approximately 2,800 archaeological artifacts. The $108 million project began in 2019 and was celebrated as complete in November 2025. The amount of work beneath the street is largely invisible once the stones are back in place.
Key facts
- NYC DDC reported a $108 million project, begun in 2019 and completed in 2025.
- Twenty-five blocks had cobblestones restored; one former asphalt block received cobblestones.
- More than 800,000 cobblestones removed and returned.
- The project added 114 pedestrian ramps and 8,800 feet of granite bicycle lanes.
- Pearl Street Plaza and stormwater and sewer upgrades were part of the project.
- Lead construction agency: NYC Department of Design and Construction.